Preliminaries
Process of plan approval including Floor plan, Elevations, Structural, Stormwater certification, BASIX, color selection, and Geotech
Process of plan approval including Floor plan, Elevations, Structural, Stormwater certification, BASIX, color selection, and Geotech
Floor slab Completion of Piers, footings, Underslab plumbing, Drainage, Electrical, Gas and Plumbing rough. structural steel and Floor slab poured
Install and bracing of prefab frames
Brickwork complete
Install of trusses, roof covering, Fascia Install, All structural support installed
Fixing, plaster and sanding complete, Cornice installed.
All framework complete. Window nailed off. External doors installed with locks. External wall cladding complete
All scope of work complete. The build can be reasonably used for their usual purpose.